The Chinese Reconciliation Park Phase 3 project includes the architectural/engineering design and construction of the following enhancement features:

  • Fencing designed with Chinese motif to screen park guests from the parking lot and nearby road.
  • Signage designed with Chinese motif, including but not limited to a welcome sign, two interpretive signs, ADA parking signs and other miscellaneous parking signs.
  • Parking lot of 30 to 40 spaces, including earthwork, drainage, paving, striping and code required landscaping.
  • Two up-lights at the Fuzhou Ting near the back corner of the park to enhance illumination and security and upgrades of the existing lights underneath the bridge to light up the parking lot.
  • Landscaping enhancement with plants including irrigation where needed.
  • Removal of approximately 1,000 cubic yards of metals contaminated soils.

Project Funding Update

SourceAmount
REET$50,000
Historical Society Grant$400,000
Open Space Fund$130,000
Total$580,000

 

Budget

Expense ItemAmount
Design$164,000
Construction Engineer$59,000
Construction$326,000
Total$549,000

 

Schedule

PhaseStart DateEnd Date
DesignJanuary 2, 2014October 31, 2014
AdvertiseDecember 16, 2014February 28, 2015
ConstructionMay 15, 2015August 8, 2015

 

Be Informed, Get Involved

You can contact City Project Manager Chris Storey (253) 573-2484, with questions, concerns or comments. You are also invited to contact Chris to get email updates on public meetings, events and notices.

 

Information shared from City of Tacoma.